Runway Centreline Lights Upgrade To CAT III At Doha International Airport (Dia)

Contract Title Runway Centreline Lights Upgrade to CAT IIIB at Doha International Airport (DIA)
Contract No. HAB/DIA-RCL/LOI-08/20-1
BEQ Job No. Q00106
Client Honeywell
Commencement Date 20-Aug-20
Contract Period 8 Months
Contract Completion Date 20-Feb-21
Expected Completion Date 20-Feb-21
Defects Liability Period/Warranty Period 24 Months

PROJECT SCOPE
1. Removal of existing runway centreline lights and Installation of new lights in CATIII B configuration
2. Trench works and Manholes for primary & secondary cabling for new Runway lights
3. Asphalt saw cutting works for secondary cable laying
4. Installation of new CCRs
5. Installation of new Illuminated Sign boards
6. Testing & Commissioning Support to Honeywell

Supply, Installation and Maintenance of Park Air and ICOM VHF radios

EXECUTIVE SUMMARY

It is an Installation & Maintenance project awarded to Bayanat Engineering Qatar from Qatar Airways (Hamad international Airport). VHF communication systems are the most widely used to communicate between ATC, Ground Handling and Aircraft.
Major Scope included Supply, installation, testing & commissioning of VHF radios and 10 Years maintenance of Park Air and ICOM Radios installed in the airside vehicles.

The equipment details mention below
1. VHF Air band Transceivers complete with accessories
2. IP based Controllers complete with accessories
3. Controllers-wired type
4. Omni directional Antenna
5. VHF Air band radio-Vehicle mountable
6. VHF Air band radio-Desktop mountable
7. VHF Air band Handheld Radio

PROJECT DETAILS

DESCRIPTION DETAILS
LOCATION Hamad International Airport
PROJECT TYPE Supply, Installation and 10 years Maintenance
APPLICATION Airport wide communications
PROJECT DESCRIPTION Supply, Installation and Maintenance of Park Air (T6TR) and ICom VHF radios (Handheld & Mobile)
Client Qatar Airways/ HIA
Project Start Date July 2017
Project Completion Date On-going (till July 2027)
Main Supplier Park Air Systems Ltd (Parkair Radios)
ICom, Japan (ICom Radios)
Project Status Active

Airport Wide Fiber Network For Atc/navaids Services At Hia Western Development Area

Contract Title : AIRPORT WIDE FIBER NETWORK FOR ATC/NAVAIDS SERVICES AT HIA WESTERN DEVELOPMENT AREA

PO No. : UBTJV-SCA-047
BEQ Job No. : Q0096 VN01
Client : UBT JV
Commencement Date : 1-Sep-20
Contract Period : 6 Months
Contract Completion Date : 28-Feb-21
Expected Completion Date : 28-Feb-21

PROJECT SCOPE
BEQ scope of works is design, supply, installation, and commissioning of Fiber network at HIA western expansion area for ATC/Navaids services

Supply & Installation Of Fiber Network And Installation Services For Agl Cms System At Doha International Airport (DIA)

Contract Title Design, Supply & Installation of Fiber Network, and installation services for AGL CMS (Aeronautical ground lighting Control & Monitoring system) at Doha International Airport (DIA)

PO No. 4415178571
BEQ Job No. Q00102
Client HONEYWELL
Commencement Date 22-June-2020
Contract Period 3 months
Contract Completion Date 22-Sep-20
Completion Date 22-Sep-20

SCOPE OF WORKS
1. Design, Supply & Installation of outdoor FIber network for AGL CMS system at DIA
2. Power infrastructure for AGL CMS system
3. Supply & Installation of Structured Cabling network inside DIA AGL Facilities.
4. Installation of AGL CMS equipment

Upgrade Of Voice Communication System (Vcs) Tmcs System At Hamad International Airport

Contract Title Design, Supply, Installation, commissioning and operational transition of FREQUENTIS voice communication system (VCS) TMCS at HIA

PO No. 2/2019
BEQ Job No. Q0074
Client Qatar Civil Aviation Authority (QCAA)
Commencement Date 18-Apr-19
Contract Period 1 Year
Contract Completion Date 18-Apr-20
Completion Date 10-Feb-20
Maintenance Support 2 Years

PROJECT SCOPE
 Design, Supply, Installation, commissioning, and operational transition of FREQUENTIS voice communication system (VCS) TMCS at HIA

Upgrade Of Communication Systems At Doha International Airport

Contract Title upgrade of Communication systems at Doha International Airport (DIA)

PO No. 07/2018
BEQ Job No. Q0070
Client Qatar Civil Aviation Authority
Commencement Date 23-Oct-2018
Contract Period 12 months
Contract Completion Date 23-Oct-2019
Completion Date 23-Oct-2019

PROJECT SCOPE
 Design Supply, Installation, Testing & Commissioning, Integration and Transition of following Communication systems at Doha International Airport

Sl. No. System Description Supplier Name
1 Voice communication system (VCS) Frequentis Austria
2 Digital Automatic Terminal Information service (DATIS) Frequentis Austria
3 Recording & Playback system (RAPS) Jotron Norway

Atc 3d Simulator Infrastructure Services For Micronav At Atc Backup Building (Buatc), Hia

Contract Title ATC 3D Simulator Infrastructure services at ATC Backup Building (BUATC), HIA
PO No. 05/2018
BEQ Job No. Q0066
Client Micronav Limited, UK
Commencement Date 5-Nov-2018
Contract Period 9 months
Contract Completion Date 5-Aug-2019
Completion Date 5-Aug-2019

SCOPE OF WORKS
 Ceiling metallic structure for supporting projectors in the 3D Tower Simulator Room.
 Raised floor plinth for the Tower Controller positions.
 Relocation of existing MEP and Low current services above ceiling to allocate space for the fixation of ceiling Metallic structure with existing I Beam at Roof.
 Power Supply for the 3D Tower Simulator room and Pseudo Pilot/Data Preparation rooms.
 Network Infrastructure for 3D Tower Simulator room and Pseudo Pilot/Data Preparation rooms. Also, the Fiber connectivity between the Simulator room and Pseudo Pilot room.
 Cooling Enhancement inside 3D Tower Simulator Room.
 Fiber Connectivity between Existing Simulator room at ATC building and New simulator
 Overall management & integration among Civil/MEP subcontractors.

Upgrade Of Airfield Lighting System At Doha International Airport (Dia)

PROJECT DETAILS
Contract Title Upgrade of Airfield Ground Lighting at Doha International Airport (DIA)
Contract No. SAP/HAB/SC/QAB000067/01
BEQ Job No. Q0082
Client Honeywell
Commencement Date 2-Sep-2019
Contract Period 12 Months
Contract Completion Date 2-Sep-20
Expected Completion Date 2-Sep-20
Defects Liability Period/Warranty Period 12 Months

PROJECT SCOPE
The Project scope includes the Installation of new Airfield Lighting equipment and related Civil/Electrical infrastructure works at Doha international Airport.

Upgrade And Phased Expansion Of Mlat System At Hia

1. UPGRADE AND PHASED EXPANSION OF MLAT SYSTEM AT HIA
1.1 PROJECT DETAILS
Contract Title Upgrade and phased expansion of Multi-lateration (MLAT) system at HIA

Contract No. 06/2019
BEQ Job No. Q0079
Client Qatar Civil Aviation Authority
Commencement Date 1-Sep-2019
Contract Period 16 Months
Contract Completion Date 30-Dec-20
Expected Completion Date 30-Dec-20
Defects Liability Period/Warranty Period 24 Months

1.2 PROJECT SCOPE
Main Scope of works in this project includes.
1. Design, supply, installation & commissioning of new MLAT system and integration with existing MLAT system at HIA.
2. 26 no’s of New MLAT ground stations at different locations inside HIA Airport
3. FO Network infrastructure connecting all the 26 Nos of MLAT ground stations to the head end MLAT cabinet located at ATC building
4. Power infrastructure for all the new MLAT ground stations
5. Any kind of Civil & MEP works required at the concerned facilities required for MLAT installation works.
6. 2 years warranty support for new MLAT system & CLS support for old components
7. Level 1/2/3 Maintenance Support

Supply, Installation , Testing & Commissioning of D-ATIS System

It was Supply and installation project awarded to Bayanat Engineering Qatar by Qatar Civil Aviation Authority (QCAA). Digital Automatic terminal information service, is a continuous broadcast of recorded aeronautical information in busier terminal areas, ATIS broadcasts contain essential information, such as current weather information, active runways, available approaches, and any other information required by the pilots, such as important NOTAMs. Pilots usually listen to an available ATIS broadcast before contacting the local control unit, which reduces the controllers’ workload and relieves frequency congestion.

Many airports also employ the use of Data-link ATIS (D-ATIS). D-ATIS is a text-based, digitally transmitted version of the ATIS audio broadcast. It is accessed via a data link service

The scope of works covered includes the following:

Hardware
1. Supply and Installation of D-ATIS Workstation positions – 5 No’s, locations:
• Tower
• Approach
• Apron
• MET
• Technical Room (Combined Client and Management Position)
2. Supply and Installation of D-ATIS Management Workstation position built into the server cabinet – 1 No’s
3. Supply and installation of operational Server -2 No’s (Redundant)
4. Supply and installation of Management Server- 1 No

Interface
Interface with existing systems listed below:
• The GAMS (Alarm and Monitoring System)
• The AFTN/AMHS
• The GDS (General Display System)
• Standard MET/AWOS interface
• The ACARS data services (SITA and ARINC)
• AGL Airfield Ground Lightening
• Radio/VCCS Interfaces (4 wire E&M interface with PTT/SQU contacts)
• Dial –In interface (standard audio interface for the integration of existing PABX)
Services

• Testing and Commissioning of the complete D-ATIS System solution.
• Operational and Technical Training